The QBP art wall, log of production phase.

Original artwork

The earlier stuff  is Here



Finishing up January with a flurry of activity.

Permits, hoists to schedule, holes to subcontract, parts to make, copper to beat. . . . . busy busy busy .
.
a few photos.

bike positioned on frame.
bike being mounted to roadway frame, the guy goes onto the steel frame at the left.

The curved section that goes around the corner of the building is on the table.

skins for the pine trees
Pine tree skins

the beat goes on
forming the texture on the deciduous trees

big tree top

Week two of January

North wall road sections all framed.
Installation contractor lined up.
Pullmax repaired - click image to see it move
.pullmax cyl
Last of the mounting brackets cut and ready to drill.
Brackets Cut
Copper cladding on most of North East roadway.
Paving the long and winding road
A start on the Bike
 the bike tires. 
Copper bike tires
Now we have started  fabricating the bike and rider.
Bike Frame Tacked together

bike welded together
Bike, sprocket and chain on floor



Where are we?
Where are we?
Red is copper clad
Blue is stuff getting ready to be clad.
The rest of the stuff is all started, and in varying states of completion.


January , here already.

Originally I had planned on building flat frames of tube and putting a copper skin over it, then things got moved to the north wall and had to jump over  roof drains.
Then the plan was skin strength box forms on a flat frame tied to the wall with simple mass produced mounts.
We were tossed a curve when  the wall maunfacturer pointed out that their wall was built to be there, stop the weather,  but  not hold any heavy unplanned load. The strength of the wall was in the heavy inside part, not the veneer over styro insulation exterior.  We had to transfer any tortion loads to the inner wall, as they might crack the veneer.

We redesigned the fasteners.to match the wall.

Rich pointed out that the wall was not flat, and I noted that the north wall venue would almost never melt and that a box structure would just pile up with snow and stay there till spring.

unless . .  

 bright ideas
The swooping road as a freeform floating ribbon suspended out from the wall on stainless trusses.  With little flat surface this would not  collect snow and the individual feet could flex enough to follow the wall's uneven surface . . . .


We have been doing a lot more work than we originally thought we would. The result will be more dynamic and will look and work better on the North wall.

Originally the flat panels were the jig and the mounts were finalized after the holes were located in the buildng. (those holes would have been drilled last week or early next and the frames would have been coming back to us to cover).
instead  each mount is unique and we have had to make huge steel jigs to locate the holes and the mount points. (the jigs will be around $2G in materials and we have to make them. BUT ! !
they make the difficult possible)

We are well on our way, it is just a different path.

The new path took some of us down unexpected paths.
Gene has spent a month working on  complex drawings to describe what we are doing to the city  and  installer. (they like box signs, they understand them, THIS variation, they want to see first)
the drawings are nearly done. . .
Pdf versions of some of the drawings.

We started on the east end of the North wall and while feeding mount point data to Cary, Gene worked on getting the drawings done ahead of the team, Rich at getting the copper textured..
As  a result  the we have a spectrum of drawings the early ones describing surface and mount points which were built off full scale printouts of the pattern and later ones  that are more detailed and are making Cary's life easier.

The frames for the first two thirds of the road are finished, (including the jig they sit on) . All the copper for that road section is textured and ready to apply (1st two on*)

The buildings  are all cut.out and ready to weld.
The trees are framed out,

The first two pieces of road are covered. . .  (*that is ahead of the orignial senario)
copper wrapped on steel frame copper on frame
1st two sections mated together Fitup at the expansion joint

The road copper is nearly finished, the tools for texturing trees and  buildings are  being  played with . . .

Unfortunately, the air cyl on the pullmax died making a repair necessary.
The old plastic rod seal disintigrated and needs to be replaced. It will be in the shop for several days but we have plenty to keep us busy without it.

broken bit of seal in cyl.
Pieces of the broken rod seal  jam under the sliding rubber seal of the  piston and let air through.
Also the old cylinder walls are badly pitted and need to be replaced.
The parts are available.

Four out of the six buildings for the city are cut

We have cut parts ready to assemble for the buildings in the city.



Cary rolls the last sections of  the S curve part of the road.